458 km of Baku - Beyuk Kesik railway section repaired in Azerbaijan

13:08 - 16.02.2018


February 16, Fineko/abc.az. Azerbaijani Railways (ADY) continues capital repairs of railroad Baku – Boyuk Kesik.

ADY reports that overhaul of the 11 km section at station Alabashli, station Soyug Bulag and section Ganja-Alabashli was launched.

"Repairs of this section will be finished within 10 days," ADY said.

ADY and Czech company MORAVIA STEEL signed on 14 April 2015 an additional agreement to the export agreement on the 2nd phase of the project of reconstruction of Azerbaijan’s railway lines. The contract says of material & technical supply and overhaul of 600 km of Baku – Beyuk Kesik railway line. To date, 458 km of railroads have been repaired within the 2nd stage.

 

 