Wartsila is starting deliveries of aggregates to Guba module power station in Azerbaijan
Baku, Fineko/abc.az. Azerenerji OJSC, national energy operator of Azerbaijan, announced successful construction of “Guba” module power station with the capacity of 105 MW (12 aggregates with capacity of 8.7MW on each). Azerenerji OJSC referring to the Station Director Javid Shalbuzov said land and concrete works on the area of 14 hectares are done. “In the near future Wartsila (Finland) will deliver the aggregates themselves. Construction of a 110 KV substation is also under completion,” Shalbuzov said. AZENKO is implementing works under control of Wartsila specialists.