Cost of restoration work In Khinalyg grew by another 2.2 million manats

12:47 - 10.10.2024


October 10, Fineko/abc.az. The amount allocated for restoration work in Khinalyg increased by another 2.2 million manats.

ABC.AZ reports that Elshan Agalarov, the head of the Capital Construction Department (under the Reserve Management Center of the State Tourism Agency), said about this  during a media tour organized on the theme "The Year of Khinalyg in UNESCO".

Explaining the reasons for the increase in costs, Agalarov said:

"The additional work has led to some increase in financing. At the first stage, 4.4 million manats were planned for 44 houses. But then there were problems with demolition. The demolition was 70%, even 100%. Then, acts were drawn up on the shortcomings, which we submitted to the Ministry of Emergency Situations. They were subsequently evaluated, and finally, it was also decided to allocate finances for 2.2 million additional works. And we continued to work on the basis of this decision."